How are Village Roads projects put out to bid?

This post discusses the process the Road Commission of Oakland County (RCOC) uses in bidding out road projects, including the Village projects and how the winning contractor bills for the project work. It also addresses how costs are accumulated and what happens if all the money in the SAD is not spent.

Background

As background, RCOC owns the Village roads. In 2018, at least 50% of the residents on every street in the Village signed “Expression of Interest” forms requesting RCOC to assess the condition of our roads and develop a plan and cost estimate to fix them. The plans and cost estimates we are working with today in petitions for the Gold and Yellow sections are the result of our request to RCOC in 2018.

After a sufficient number of residents of a section sign petitions in support of fixing their roads, Bloomfield Township conducts the first public hearing — the Hearing of Necessity. Residents can express their opinions, both for and against the project, and the Township Trustees will vote on whether to advance the project to the next step — requesting RCOC to finalize the project plans and bid the project.

Finalizing project plans

RCOC develops a detailed engineered plan for each street and accumulates the construction steps and materials into “pay items”. For each Pay Item, RCOC:

  • Lays out specifications defining the requirements for that item, for example:

    • specific material to be used, including specific quality requirements;

    • specific measures for the material (for example, 4 inches of crushed stone);

    • specific equipment to be used;

    • specifications on how it is to be performed (full width paving, for example);

    • testing that it must meet when completed; and

    • other elements specific to that construction step.

      The specifications for the Pay Items are accumulated into a specification book; the spec books for the PINK and BLUE section projects run 162-164 pages for about 30 Pay Items.

  • Accumulates total project quantities for that Pay Item.

The bid package will lay out a list of Pay Items, with associated quantity for that Pay Item.

Bidding Process

RCOC utilizes a national portal, BidExpress, to bid all of its road projects, including the Village projects. BidExpress is an open portal, available to any contractor interested in bidding on RCOC projects. (One doesn’t need to be a contractor to open an account in BidExpress - residents can register for a free account, see below.) The process:

  • RCOC posts “request for bid” for the project in BidExpress. The request for bid includes:

    • engineering plans for the project;

    • list of Pay Items and quantities for each Pay Item;

    • the specifications book;

    • due date and time for final bids.

      For example, the bid packages for the PINK and BLUE sections were posted on March 5, 2024, with bids due at 11 am on March 26, 2024.

  • RCOC places advertisements in local papers and in trade publications to advertise the request for bid. Road contractors also utilize various tools through BidExpress and trade publications to be notified when projects are posted for bidding.

  • During the period the project is open for bidding, one can see the contractors accessing the bid packages in BidExpress. However, no bidding information is available or visible.

  • On the date and time specified in the request for bid, bidding is closed. Once bidding is closed, the bids for the project are opened on-line. Upon bid opening, contractors who bid and their bids, including costs for each Pay Item and the total bid, are visible on BidExpress from that point forward. The lowest qualified bidder wins the contract.

    • If the lowest bidder is not known to RCOC, they will investigate the contractor to ensure they have the qualifications to do the job (investigate background, whether they have the requisite experience and equipment, etc.) If the lowest qualified bidder is not qualified to do the work, the next lowest bidder will be awarded the work.

Once the winning bid is accepted, RCOC and the winning bidder will enter into contracts for the work.

Project Costs

Throughout the project, RCOC and its inspectors are on site every day, ensuring that the contractor and sub-contractors are performing the work in accordance with the project specifications. Materials are tested and work is inspected; and if they don’t meet the specification, the contractor will have to redo the work on his own dime. Materials used are measured to ensure the project is billed only for what is actually used. Various construction steps are counted (drainage structures lined, drainage structures replaced, fire hydrants moved, ADA ramps installed, for example); the contractor can only bill for work actually performed to the RCOC specifications. The contractor bills for actual quantities/work at the prices quoted in the bid. If there are Pay Items (mailboxes, for example) that are included in the bid, but for which no work is done, nothing can be billed for that Pay Item. There are a handful of Village street signs that may need to be removed and reinstalled during the project; the “mailboxes” line item may be where that work would be billed.

One Pay Item that has raised questions from some residents is “Maintaining Traffic.” This Pay Item will include all the signage for the project, cones, barricade, etc., as well as the labor required to move signs/barricades/cones, etc. throughout the project. Flaggers and other workers involved in directing traffic during the project fall under this Pay Item too. It may also include other costs and/or some element of contractor profit. Of note, there are no Pay Items for mobilization costs or project management by the lead contractor (which is Ajax Paving for the Pink and Blue sections). Contractors can take different approaches to their bids. Some may include mobilization and project management costs as part of the individual Pay Items; others may include such costs as part of “Maintaining Traffic”, while others may use some combination of those approaches. “Maintaining Traffic” may also be the Pay Item contractors use to adjust their overall price to compete for the project and try to ensure they are the lowest bidder.

Project billings

Project billings submitted to the Road Commission will include quantities being billed for each Pay Item, priced at the quoted unit price for that item per the contractor’s bid. Where quantities used on the project or work performed on the project exceeds the estimated quantity in the bid, the contractor will be paid for the actual quantity. (That is, the total the contractor is paid for that Pay Item will be more than the amount bid, because there was more work done.) Similarly, if the quantity of material actually used or work actually performed is less than the estimated quantity in the bid, the contractor is only paid for the actual material used/work performed, at the price quoted in the bid. The Road Commission reviews and validates the contractor’s billings. Bloomfield Township utilizes proceeds from the bonds sold to fund the project to pay the Road Commission for the project costs.

What happens when the project is completed?

All costs incurred in the project are accumulated by Bloomfield Township and accounted for separately from other SADs or the general funds of the Township. Once all costs are incurred and all of the assessments are collected over the 15-year term of the SAD, there may be money left over in the SAD. By statute, if the excess in the SAD is more than 5% of the total SAD cost, that excess must be refunded to the residents at the end of the 15-year term of the SAD. If excess is less than the 5% threshold, by statute, the money is to be retained by Bloomfield Township; Township policy provides that the funds are to be used for maintenance of the roads improved by the SAD.

How do I access bidding information?

Bid information is available on BidExpress. You will need to set up a log-in first — this is free and takes about 5 minutes to do.

Step 1 — create a log-in for BidExpress.

  • Go to BidExpress.com. Toward the bottom of the page, you will see a “user log-in” option. Click on “create vendor account” to the right of the “user log-in” button.

  • Enter the email you want to use for your account and click “continue”. this will take you to a form you will need to fill out. You will have to enter a company name and address — you can use “Village resident” or your own name in that field. Make sure to enter the password you want to use. Once you have filled out the form and submitted it, the website will send a verification code to the email address you entered.

  • Fill in the verification code; you will then be asked for your password. This will take you to your home page on BidExpress. if you see a pop-up asking whether you want to upgrade your membership, just hit the “X” in the upper right corner of the pop up.

Step 2 — Find the bidding information

  • From your BidExpress homepage, click on the “Solicitations” tab. In the search bar, enter “Road Commission for Oakland County”. In the Filters section at the left, change the status to “Closed” and hit the “search” icon (looks like a magnifying glass. This will bring up a list of projects on which the bidding has closed. Scroll down and you will find the Pink (they call it Red) and Blue section projects.

  • Click on the project number to be taken to the page for the individual project. Once there, scroll down to see the list of bids received and the amount bid by each contractor. For bid detail, scroll back to the top, selected the “reports” option and it will pull up the bidding detail for each bidder.

  • An alternative means to access Road Commission’s bids — https://www.bidexpress.com/businesses/8638/home.

Previous
Previous

Are there other, less expensive options than rebuilding our roads?

Next
Next

Construction Update - BLUE section 9/18/24