The schedule for asphalt removal (milling) this week in both the PINK and BLUE sections has been updated. The revised schedule follows:

Wednesday, October 16 — N. Williamsbury in the Blue section, then the portion of Tilbury north of Pine (Pink section), then the block of Yarmouth that runs from Cranbrook north to Oak (Pink section).

Thursday, October 17 — Oak Blvd. from Covington to Birmingham, then the block of Yarmouth that runs from Oak north to Cranbrook.

Friday, October 18 — Dorstone, then Tottenham

Grading on each street will begin in the days following milling.

Parking and access restrictions during milling and grading

Please see discussion of parking, driveway access and traffic restrictions during milling and grading, including parking suggestions, for:

During asphalt removal, the mill will move slowly down the street, blocking the entire width of the road. Traffic will have to detour around the mill. When Oak is milled on Thursday 10/17/24, residents who normally use that route to Quarton Elementary or into Birmingham will have to find an alternative.

Previous
Previous

Construction Update — PINK section 10/16/24

Next
Next

Construction update — PINK section 10/9/24